Brunswick Central School District Troy, NY

Starting installation of new wood sports flooring in High School gym.

Framing and plumbing for new Nurse's office suite at the Parker School.

Preparing for installation of energy saving, thermally insulated storefront at the High School.

Refurbishing of the auditorium has begun.

New asphalt sidewalks on the Brunswick campus - June 2008.

New field storage building on the Brunswick Campus.

High School team locker room reconstruction is underway.

The loading dock at the HS/MS is nearing completion.

The Middle School stage has been removed and reconstruction of classroom on the main floor is set to begin.

Construction of new offices, break room and mezzanine are nearing completion at the Bus Garage.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 
 

Albany Community Charter School
Bethlehem CSD
Brunswick CSD
East Greenbush CSD
Green Tech High Charter School
Massry Center for the Arts
Niskayuna CSD
Saint Francis Hospital ED

 

 

This $10.1 million project consists of renovating and refurbishing Tamarac Elementary School, Parker School, Tamarac Middle and High Schools, the Bus Garage and Field Storage Building.  The project was bid June 2007 and work commenced in July.  See below for a more detailed description of the work to be performed. 

 

Additional information about the District can be viewed at the Brunswick Central School District's website www.brittonkill.k12.ny.us/.

 

Architect: CS Arch, PC

 

WORK CURRENTLY UNDER CONSTRUCTION

Tamarac High/Middle School

  • Replace main entrance canopy.
  • Replace 1957 gym floor, bleachers and room divider.
  • Refinish middle school gym floor; replace room divider.
  • Replace single pane aluminum storefronts and doors.
  • Refurbish corridor tile walls and terrazzo lobby floor.
  • Replace kitchen cooler; improve make-up and exhaust system.
  • Replace fixtures in second floor toilet room in 1957 wing.
  • Complete conversion over to energy-efficient mechanical controls.
  • Mechanical system upgrades.
  • Improve HVAC and electric services in IT server area.
  • Replace selected electrical panels.
  • Installation of additional and improved camera security system equipment.
  • Provide new phone system and phones; train and “cut-over” to new phone system.  
  • Installation of site light poles along Rt. 2.

Work started after Graduation 2008 and scheduled for mid-fall 2008 completion:

  • Refurbish auditorium carpet, seats, stage surface, finishes, curtain, etc.
  • Construct new sound booth, enhance sound controls.
  • Install improved auditorium HVAC ductwork.
  • Refurbish auditorium and stage lighting and power systems.

Tamarac Elementary School

  • Replace selected interior doors and hardware
  • Refinish gym floor
  • Replace selected areas of ceiling tiles.
  • Replace HVAC equipment and upgrade mechanical systems.
  • Install upgrades for energy-efficient mechanical controls.
  • Provide new phone system and phones; train and “cut-over” to new phone system.  
  • Installation of additional and improved camera security system equipment.

Parker School

  • Replace/repair sections of exterior concrete block walls.
  • Repair exterior soffit; install infill panels where roof deck exposed.
  • Paint exterior block walls and soffit.
  • Demo and reconstruct Nurse's office and toilet room areas.
  • Replace hollow metal exterior doors.
  • Install accordion door between two north classrooms and new entry doors for those classrooms.
  • Replace selected interior doors and hardware.
  • Replace gym windows.
  • Install new cabinetry in classroom for science use.
  • Install new cabinetry in kitchen and Nurse's office areas.
  • Replace classroom and office heating systems with added ventilation controls.
  • Replace boilers, pumps and controls.
  • Remove existing and install new electric service entrance to building and distribution; replace existing electrical panels throughout building.
  • Improve energy efficiency and exhaust systems.
  • Complete augmentation/replacement of fire alarm and other safety systems.
  • Install exterior site lighting.

Bus Garage

  • Repair concrete floor in maintenance area.
  • Replacement of railing on existing mezzanine.
  • Upgrade security systems.

 

WORK COMPLETED: Summer-Fall 2007 thru late Spring 2008

Site Work and Storage Building at Tamarac Site

  • Reconfigured traffic and parking at both the high school and elementary school loops for improved safety.
  • Added paved and striped parking area at southeast corner of site for additional parking spaces.
  • Removed bases for abandoned site lighting, ran conduits across new paved area for new site lighting, reinstalled and energized salvaged round head site lights in drop-off islands.
  • Reinstalled school information sign at main vehicle entrance.
  • Installed additional directional signage.
  • Resurfaced and restriped running track.
  • Demolished old wood storage building; provided new foundation, concrete block, and shingle roof storage building replacement; restored adjacent paving, fences and grass.
  • Installed concrete bases for site lighting, installed all site lights away from Rt. 2.

Tamarac High/Middle School

  • Replaced roofs at HS and MS gym with new foam insulated roofing system.
  • Asbestos abatement of VAT in southwest first floor classrooms, north corridor, and one second floor classroom.
  • Installed of VCT flooring and base in those same rooms and corridor prior to start of classes for fall of 2007.
  • Enlarged IT server room and provided IT office space.
  • Relocated water line, hydrant, and irrigation system feed/meter around new loading dock location.  Restored sidewalks, paving and grass at loading dock addition.
  • Installed foundation, walls, roof structure, and utilities for new loading dock addition.  Modified areas of existing building for access and exit corridors, walls, etc...
  • Removed middle school stage in Cafetorium (including concealed ACM) and reconstructed area into classroom at main floor elevation.
  • Replaced unit ventilators, windows, and window sills in selected rooms and corridors (mostly 1970’s addition).
  • Provided mechanical system upgrades.
  • Provided additional electric in computer classroom.
  • Installed conduit, wiring, lighting and device improvements to electrical and safety systems throughout school building.
  • Selected lighting upgrades and provided occupancy sensors for lighting.
  • Installed improvements to safety systems.
  • Installed system equipment and “backbone” wiring for new phone system.

Tamarac Elementary School

  • Replaced older roofing system with new foam insulated roofing
  • Asbestos abatement of all remaining VAT in classrooms, cafeteria, coach’s office, and two small rooms.
  • Patched the concrete floors in those same rooms and installed VCT and base prior to start of classes.
  • Asbestos abatement of pipe elbows in south wall of large gym.
  • Reinforcement of the south wall of large gym and reinstallation of wallboard, taping and pads prior to start of classes for fall of 2007.
  • Demolition and removal of cafeteria stage and restoration of finishes for expanded cafeteria area.
  • Refurbished selected toilet room fixtures and classroom sink trims.
  • Selected lighting upgrades and provided occupancy sensors for lighting.
  • Installed improvements to safety systems.
  • Replaced selected electrical outlets and devices.
  • Installed additional electric panel; provided electrical modifications for new HVAC.

Parker School

  • Removed older playground equipment.
  • Removed and replaced damaged areas of existing foam insulated roofing system and installed refinish coat over entire low roof system.
  • Replaced roof at gym with new foam insulated roofing system.
  • Asbestos abatement of VAT in nurses area, one classroom, the existing back office suite, and Cafetorium; abatement of pipe elbows found under the removed stage and over the removed gym soffit.
  • Patched the concrete floors in those same rooms and installed VCT and base in classroom prior to start of classes.
  • Demolished and removed of Cafetorium stage and back office area walls; reconstructed into new office area with new HVAC, etc.
  • Installed new flooring and base in Cafetorium.
  • Installed conduits, wires, devices, etc. for additions to the fire alarm system.
  • Upgraded electrical outlets and devices.
  • Installed conduits for new electric service panels throughout building.
  • Upgraded selected interior lighting and controls.

Bus Garage

  • Excavation and installation of storm water drainage along Tamarac Road side of building.
  • Demo and repairs to foundation wall along back wall of bus storage area. 
  • Installation of drainage in floor along back of bus storage area.
  • Asbestos abatement of VAT in existing office and break rooms.
  • Demo of existing and construction of new offices, toilet rooms, break room and mezzanine.
  • Installed railing on new mezzanine.
  • Installed replacement doors and hardware in bus and maintenance areas.
  • Replace 2nd lift to meet current standards.
  • Completed new hot water heater and plumbing for offices and break room.
  • Completed new HVAC system with air conditioning for office area.
  • Installed new exhaust fans for bus storage area.
  • Upgraded interior lighting in bus and maintenance areas.
  • Removed existing and install new electric service panels and distribution.
  • Completed new electrical systems in office area and in bus and maintenance areas.
  • Replaced fire alarm system.
  • Installed new exterior site lighting on building and pole lights.

 

Updated:

August 2008